Court Summary - at a glance

Date of offence:
Between 14 and 20 March 2018
 
Plea:
Guilty
 
Decision:
Convicted
 
Final decision date:
 
Fine imposed:
$12,500

Safety lessons learned:

Build Northland Limited should have:

  • Developed, documented, implemented, communicated, and monitored compliance with an adequate safe system of work for the installation of the attic trusses;
  • Used a crane to place the trusses (ensuring that the workers were able to install and fix from the exterior scaffolding with the safety nets in place).

Defendant name:
Build Northland Limited
 
Industry:
Building and construction
 
Date of offence:
Between 14 and 20 March 2018
 
Facts in brief:
The Defendant is a residential construction company that has operated as a franchisee of Landmark Homes since 2014. They were engaged to build a residential home in Whangarei.

A worker was left permanently paralysed when he fell approximately two metres to the ground from an aluminium plank and landed on his head.
 
Offence section:
Sections 48(1) and 2(c), and 36(2) of the Health and Safety at Work Act 2015
 
Date(s) charged:
14 March 2019

Court:
Whangarei - District Court
 
Plea:
Guilty
 
Final decision date:
 
Decision:
Convicted
 
Fine imposed:
$12,500
 
Maximum fine available:
$1.5 million
 
Reparation:
$100,000 for emotional harm
$51,578.21 for consequential loss